Chamonix: Adjustments in the investments and new calendar for works on the ski area

Friday 20th October 2017, during the city council, the elected representatives of the Community of Communes of the Chamonix valley made some adjustments concerning certain investments in the ski area.

According to Le Dauphine, the replacement of the current Charamillon gondola, scheduled for 2017, is delayed to allow time for discussion with the inhabitants of the village of Le Tour.

Instead, unscheduled works were carried out in 2017 with the joint agreement of the Community of Communes: the artificial snow work at the Grands Montets area (on the slope of Coqs and Combes); also shortening is planned for the Col de Balme ski lift.

A new calendar for works on the ski area

Here is the calendar until 2020:

  • Works for the renovation of the artificial snow network on La Flégère and Le Savoy will continue this year 2017.
  • Christmas 2018: will go into service the chairlift in Lognan, called to replace the chairlifts of Marmottons and Tabé, initially planned in 2019. And the beginners area, initially planned in 2024.
  • Christmas 2019: will go into service the gondola that will replace the Flégère cable car.
  • 2020: The new Charamillon gondola is postponed until the winter of 2020.
Chamonix: Izipizi s’associe à ZagSkis pour lancer des lunettes de glacier en édition limitée
Chamonix: Des ajustements dans les investissements et nouveau calendrier des travaux sur le domaine skiable